Which statement is false?

Prepare for your Construction Manager in Training Test with comprehensive questions, expert explanations, and study tools. Boost your confidence for exam success!

Multiple Choice

Which statement is false?

Explanation:
Under CMAA, the CM-at-Risk arrangement defines the construction manager as the manager who delivers the project with financial risk, not as the owner’s legal agent for contract administration. If the owner could direct the CM to act as an agent of the owner under a CM-at-Risk contract “without penalty,” that would blur the line between the CM’s role and an agency relationship, which the CM-at-Risk form does not establish. If the owner wants the CM to act as an agent, the appropriate path is the Agency form, which creates that agent relationship and its specific authorities.

Under CMAA, the CM-at-Risk arrangement defines the construction manager as the manager who delivers the project with financial risk, not as the owner’s legal agent for contract administration. If the owner could direct the CM to act as an agent of the owner under a CM-at-Risk contract “without penalty,” that would blur the line between the CM’s role and an agency relationship, which the CM-at-Risk form does not establish. If the owner wants the CM to act as an agent, the appropriate path is the Agency form, which creates that agent relationship and its specific authorities.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy